PT Rizal Jaya
Main Roads & ArterialsStatus: Completed on Schedule

Sector 2-3 & 9 Main Road Patching (2025)

location_onArterial Corridors Sector 2, 3, and 9 Bintaro Jaya

Sector 2-3 & 9 Main Road Patching
Final Field Documentation

Sector 2-3 & 9 Main Road Patching

location_onProject Location

Arterial Corridors Sector 2, 3, and 9 Bintaro Jaya

apartmentClient / Developer

Bintaro Jaya

layersMaterial Type

Hotmix Asphalt AC-BC & AC-WC Patching

square_footEstimated Area

± 1,800 m² (Dispersed Patching Spots)

scheduleExecution Duration

4 Calendar Days

Scope of Work

About the Project

Rapid-maintenance asphalt program remedying potholes and localized subgrade depression across high-traffic intersections.

Employing cold-milling saw cutting, debris extraction, emulsion tack coat, and rapid roller compaction with flush seamless joints.

Committed to genuine AMP material quality and veteran workmanship, PT Rizal Jaya Construction ensures every inch of pavement achieves uniform density, wave-free smoothness, and optimal rainwater runoff.

verifiedPrime Compaction Control

Precision mechanical compaction using tandem rollers ensures asphalt does not easily sag or form hairline cracks.

water_dropElevation & Water Runoff

Road edges are calibrated precisely along curbs and culverts to prevent rainwater accumulation.

SPECIFICATION DATA

Technical Specifications & Machinery

layersMain Materials Used

  • check_circleAsphalt Saw Blades
  • check_circleHigh-Temperature Hotmix
  • check_circleTack Coat

precision_manufacturingHeavy Machinery Deployed

  • buildAsphalt Cutter
  • build2-Ton Baby Roller
  • buildTamper Compactor

fact_checkQuality Control Standards

  • verified_userFlush Seamless Jointing
  • verified_userZero Tire Bump Impact
workspace_premium
Quality Warranty & Guarantee

Anti-Settling Joint Warranty

Field Documentation

Documentation Gallery

Visual documentation of paving stages from site preparation to final compaction.

Site Preparation & Road Cleaning
Stage 01

Site Preparation & Road Cleaning

Clearing dust, moss, and loose soil using high-pressure air compressors to ensure maximum asphalt adhesion.

Tack Coat Emulsion Spraying
Stage 02

Tack Coat Emulsion Spraying

Evenly spraying cationic asphalt tack coat across the subgrade before hotmix asphalt application.

Precision AC-WC Hotmix Laying
Stage 03

Precision AC-WC Hotmix Laying

Spreading hotmix asphalt at optimal temperatures (110°-150°C) to maintain density and structural flexibility.

Tandem Roller Compaction on Residential Lanes
Stage 04

Tandem Roller Compaction on Residential Lanes

Repeated mechanical rolling with 4-6 ton Tandem Rollers for a dense, sturdy, and watertight pavement.

Edge Profiling & Drainage Alignment
Stage 05

Edge Profiling & Drainage Alignment

Calibrating road edge elevations against curbs and gutters to ensure rainwater drains smoothly without puddles.

Finished Smooth Asphalt Pavement
Stage 06

Finished Smooth Asphalt Pavement

Level, durable, and clean hotmix asphalt roadway open to residential traffic with guaranteed durability.

Similar References

Related Projects & Works

View All Projectsarrow_forward
Cluster Kucica Residential Paving
Bintaro Jaya

Cluster Kucica Residential Paving

Neighborhood road rejuvenation in Cluster Kucica Bintaro Jaya was executed as a strategic enhancement of mobility and aesthetic value for an exclusive residential estate.

View project details
Cluster Cikini 3 Residential Paving
Bintaro Jaya

Cluster Cikini 3 Residential Paving

Enhancing internal residential road quality in Cluster Cikini 3 for smooth and safe daily vehicle mobility.

View project details
Sector 3 Main Road Paving
Bintaro Jaya

Sector 3 Main Road Paving

Reconstruction and asphalt overlay on Sector 3 arterial corridors to ensure smooth flow for heavy daily commuter traffic.

View project details
handymanFREE TECHNICAL CONSULTATION & SITE SURVEY

Need Similar Asphalt Paving Work?

Consult your hotmix paving or infrastructure project needs with PT Rizal Jaya Construction. Free site survey & transparent cost estimate.