Residential PavingStatus: Completed on Schedule

Cluster Cikini 3 Residential Paving (2025)

location_onCluster Cikini 3, Bintaro Jaya Sector 7, South Tangerang

Cluster Cikini 3 Residential Paving
Final Field Documentation

Cluster Cikini 3 Residential Paving

location_onProject Location

Cluster Cikini 3, Bintaro Jaya Sector 7, South Tangerang

apartmentClient / Developer

Bintaro Jaya

layersMaterial Type

Hotmix Asphalt AC-WC & AC-BC

square_footEstimated Area

± 3,800 m²

scheduleExecution Duration

6 Calendar Days

Scope of Work

About the Project

Enhancing internal residential road quality in Cluster Cikini 3 for smooth and safe daily vehicle mobility.

Work focused on subgrade re-leveling, uniform tack coat application, and precision tandem roller compaction, yielding a dense, watertight, and durable asphalt surface.

Committed to genuine AMP material quality and veteran workmanship, PT Rizal Jaya Construction ensures every inch of pavement achieves uniform density, wave-free smoothness, and optimal rainwater runoff.

verifiedPrime Compaction Control

Precision mechanical compaction using tandem rollers ensures asphalt does not easily sag or form hairline cracks.

water_dropElevation & Water Runoff

Road edges are calibrated precisely along curbs and culverts to prevent rainwater accumulation.

SPECIFICATION DATA

Technical Specifications & Machinery

layersMain Materials Used

  • check_circleHotmix Asphalt AC-WC
  • check_circleCationic Tack Coat Emulsion

precision_manufacturingHeavy Machinery Deployed

  • build4-Ton Tandem Roller
  • buildBaby Roller
  • buildAsphalt Sprayer

fact_checkQuality Control Standards

  • verified_userBina Marga Technical Standards
  • verified_userPlacement Temperature 120°C - 150°C
workspace_premium
Quality Warranty & Guarantee

Official Maintenance Warranty

Field Documentation

Documentation Gallery

Visual documentation of paving stages from site preparation to final compaction.

Site Preparation & Road Cleaning
Stage 01

Site Preparation & Road Cleaning

Clearing dust, moss, and loose soil using high-pressure air compressors to ensure maximum asphalt adhesion.

Tack Coat Emulsion Spraying
Stage 02

Tack Coat Emulsion Spraying

Evenly spraying cationic asphalt tack coat across the subgrade before hotmix asphalt application.

Precision AC-WC Hotmix Laying
Stage 03

Precision AC-WC Hotmix Laying

Spreading hotmix asphalt at optimal temperatures (110°-150°C) to maintain density and structural flexibility.

Tandem Roller Compaction on Residential Lanes
Stage 04

Tandem Roller Compaction on Residential Lanes

Repeated mechanical rolling with 4-6 ton Tandem Rollers for a dense, sturdy, and watertight pavement.

Edge Profiling & Drainage Alignment
Stage 05

Edge Profiling & Drainage Alignment

Calibrating road edge elevations against curbs and gutters to ensure rainwater drains smoothly without puddles.

Finished Smooth Asphalt Pavement
Stage 06

Finished Smooth Asphalt Pavement

Level, durable, and clean hotmix asphalt roadway open to residential traffic with guaranteed durability.

Similar References

Related Projects & Works

View All Projectsarrow_forward
Cluster Kucica Residential Paving
Bintaro Jaya

Cluster Kucica Residential Paving

Neighborhood road rejuvenation in Cluster Kucica Bintaro Jaya was executed as a strategic enhancement of mobility and aesthetic value for an exclusive residential estate.

View project details
Sector 3 Main Road Paving
Bintaro Jaya

Sector 3 Main Road Paving

Reconstruction and asphalt overlay on Sector 3 arterial corridors to ensure smooth flow for heavy daily commuter traffic.

View project details
Sector 9 Main Road Paving
Bintaro Jaya

Sector 9 Main Road Paving

Asphalt resurfacing across Sector 9 commercial and culinary corridors with high weekend and evening vehicle traffic.

View project details
handymanFREE TECHNICAL CONSULTATION & SITE SURVEY

Need Similar Asphalt Paving Work?

Consult your hotmix paving or infrastructure project needs with PT Rizal Jaya Construction. Free site survey & transparent cost estimate.